top of page

4th Street -
Civic Campus

LATEST
NEWS/UPDATES 

Entry Perspective (larger resolution) with sky.jpg

Here you will find any and all information on our current progress and operations regarding the 4th Street Property.  This site is best viewed in DESKTOP MODE.

Next Up...

If you wish to see how the Fire District and the City's individual projects will look upon completion, thus forming the Civic Campus, follow the link below.
https://www.snohomishwa.gov/817/Public-Safety-City-Services-Campus

4th Street
Fire Station Progress
10.13.2025 - 10.17.2025

OCTOBER 16, 2025

~ Schedule Update 10.23.2025 ~

Week of 10/27

  • Continue Framing 

  • MEPF (Mechanical, Electrical, Plumbing) Rough-in 

  • Continue Roofing 

  • Widow Wrap install 

  • Complete Pine Water Main 

  • JUT (Joint Utility Trench) install with Sno-Pud on site 

  • Continue Infrastructure hardscapes (curbs and sidewalks)

 

Week of 11/3

  • Continue Framing 

  • MEPF Rough-in 

  • Continue Roofing 

  • Widow Install 

  • Start WRB install 

  • CMU (concrete Masonary Unit) site wall foundations 

  • JUT Install 

  • Sno-Pud Service Pole install 

  • Continue Infrastructure hardscapes 

 

Week of 11/10

  • Complete Framing 

  • MEPF Rough-in 

  • Continue Roofing 

  • WRB (building wrap) install 

  • Base of wall flashings install (prep for brick)

  • Brick install start 

  • JUT Install 

  • Sno-Pud Service Pole install 

  • Continue Infrastructure hardscapes 

 

Week of 11/17

  • MEPF Rough-in 

  • Hollow Metal Door Frame install 

  • Steel Stair Install 

  • Continue Roofing 

  • WRB install 

  • Continue brick install

  • Complete JUT Install 

  • Continue Infrastructure hardscapes 

OCTOBER 16, 2025

~ Schedule Update 10.16.2025 ~

Week of 10/20

  • Continue framing 

  • Start roofing 

  • Mechanical/Electrical/Plumbing (MEPF) rough-in 

  • Exterior (siding) Mock-up Install

  • Pine Utility Trench (JUT) install 

  • Infrastructure Hardscapes (curbs/sidewalks) install 

 

Week of 10/27

  • Continue framing 

  • Continue roofing 

  • MEPF rough-in 

  • Window Wraps & Rough-opening waterproofing 

  • Pine JUT install 

    • Sno-pud conducting pole holds

  • Infrastructure Hardscapes install 

 

Week of 11/3

  • Complete mass framing 

  • Continue roofing 

  • MEPF rough-in 

  • Vinyl windows install 

  • WRB (building wrap) Install Start 

  • Pine Storm (Between 3rd and 2nd )

  • Infrastructure Hardscapes install 

 

Week of 11/10

  • interior framing 

  • Continue roofing 

  • MEPF rough-in 

  • Continue WRB Install 

  • Brick Veneer Start 

  • Infrastructure Hardscapes install 

OCTOBER 6, 2025

~ Schedule Update 10.6.2025 ~

Week of 10/6

  • Finish Station Floor Grinding/ Protection 

  • Continue Framing Walls 

  • Start Framing Roof System 

  • Exterior Mock-up for siding

  • Continue Utility Trench install 

  • Complete Pine Side Sewers 

  • Start Pine Storm 

​

Week of 10/13

  • Continue Framing Walls 

  • Continue Framing Roof System 

  • Start Roofing 

  • Start “In wall” Mechanical, Electrical, and Plumbing (MEPF)

  • Excavate and place site wall footings 

  • Continue Utility Trench install 

  • Pine Water Main Install 

  • Start Infrastructure Hardscapes (curbs/sidewalks)

 

Week of 10/20

  • Continue Framing Walls 

  • Continue Framing Roof System 

  • Continue Roofing 

  • Continue in-wall MEPF's 

  • Metal door frame install 

  • Complete Utility Trench install 

  • Continue Hardscapes 

  • Onsite Grading for Station site

​

Week of 10/27

  • Completion of Bulk Framing 

  • Continue Roofing 

  • Continue in-wall MEPF's

  • Start window install 

  • Complete Hardscapes 

SEPTEMBER 26, 2025

~ Schedule Update 9.25.2025 ~

Week of 9/29

  • Continue Utility Trench Install 

  • Pine Sewer Stub (to residents) Install 

  • Cypress/4th St Storm Install 

  • Cypress Water Install 

  • Framing of Fire Station Starts

  • Continue Concrete Floor Grinding/Polishing for Fire Station

 

Week of 10/6

  • Continue Utility Trench Install 

  • Pine Water Install 

  • Cypress Water Fill/ Testing 

  • Cypress Water Tie-in 

  • Continue Framing of Fire Station

  • Start of Roof Framing 

  • Continue floor Concrete Floor Grinding/Polishing

 

Week of 10/13

  • Utility Trench road Crossings 

  • Pine Water Service (residents) Install 

  • Pine Storm Install 

  • 4th & Cypress Hardscapes- Sidewalks, curbs, etc

  • Continue Framing of Fire Station

  • Mechanical/Electrical/Plumbing Rough-in Start (Fire Station)

  • Roofing Starts

 

Week of 10/20

  • Complete Utility Trench

  • Fire Station Utilities Tie-in to Pine 

  • Pine Hardscapes – sidewalks, curbs, etc

  • 4th & Cypress Paving 

  • Continue Framing – Fire Station

  • Continue Mechanical/Electrical/Plumbing Rough-in 

  • Continue Roofing 

SEPTEMBER 18, 2025

~ Schedule Update 9.18.2025 ~

Week of 9/22

  • Start of floor grinding (concrete)

  • Floor protection install 

  • Framing material deliveries 

  • Site wall foundations 

  • Start of Pine Utility trench

  • Sno PUD Pole install 

  • Pine Sewer Stub install 

  • Cypress & 4th Storm install 

 

Week of 9/29

  • Continue floor grinding (concrete)

  • Framing start 

  • Continue Pine Utility Trench

  • Pine Water install 

  • Complete/test Cypress water main 

​

Week of 10/6

  • Complete floor grinding 

  • Continue framing 

  • Complete Pine Utility Trench

  • Pine Water Services install 

  • Pine Storm 

 

Week of 10/13

  • Continue framing 

  • Mechanical/electrical/plumbing rough-in start 

  • Roofing start 

  • Infrastructure Hardscapes/ Pavement restorations

SEPTEMBER 10, 2025

~ Schedule Update 9.10.2025 ~

Week of 9/15

  • Completion of onsite utilities

  • On site grading

  • Pine Ave Sewer start

  • 3rd St & "Old Cypress" Utility Trench start

 

Week of 9/22

  • Floor grinding & floor protection install

  • Framing materials delivery start

  • Pine Ave Sewer Stub install

  • Pine Ave Utility Trench start

​

Week of 9/29

  • Station/building framing start

  • Floor grinding & floor protection

  • Pine Ave Utility Trench install

  • Pine Ave Water Main install

 

Week of 10/6

  • Continue framing

  • Floor grinding and floor protection

  • Pine Ave Water services install

  • Pine Ave Storm install

SEPTEMBER 4, 2025

~ Schedule Update 9.4.2025 ~

Week of 9/8

  • Completion of on-site utilities

  • Slab on grade cure

  • Fire Drive "Old Cypress" Water Installation

  • 3rd St Water Main Tie-in

​

Week of 9/15

  • Slab on Grade Cure

  • Start of wall panel delivery

  • Pine Sewer Install Start

  • Pine Utility Trench

  • 3rd & 4th St Sidewalk restoration

​

Week of 9/22

  • Floor Grinding within Area one

  • Continue Wall Panel Delivery

  • Pine Side Sewer Stub Install (home connections)

  • SnoPud Pole Install on Pine

​

Week of 9/29

  • Standing walls within Area one

  • Floor Grinding within Area two

  • Pine Water Main Install

  • 3rd St Utility Trench Install (between Pine & Cypress)

AUGUST 25, 2025

Please note that the contractor will be start work early on Thursday, due to the weather and type of work. See below for details and don’t hesitate to let me know if you have any questions.

 

Date and Time: Thursday 8/28/25 from 6am- 7am 

 

Work Taking Place: Placing the slab on grade within the apparatus bay of the FS#41. Concrete placement will be 200 yards placed with a pump truck. 

 

Reason For Off Hours: with the hot weather and the size of the placement the crews will need to take advantage of the early hours of the day. With the earlier placement we will mitigate and pre-mature hardening of the slab and ensure that the proper quality requirements are met. 

 

Sound mitigation: the concrete trucks that will be on site are all equipped with low frequency back-up alarms. Prior to start of placement the pump truck operator will be briefed and the horn on the pump truck will be disabled between the hours of 6am-7am. During that time the pump truck operator will use alternate means to communicate with the truck drivers.  Placement of the concrete will also begin in the Southwest corner of the site so the concrete vibrator will be the furthest away from any residents.  

AUGUST 21, 2025

~ Schedule Update 8.21.2025 ~

Week of 8/25

  • Building Slab prep and pour

  • On site utilities

  • "Old Cypress" Now Fire Dr- sewer completion and testing

  • Pine Sewer Prep

  • Fire Dr water main install

 

Week of 9/1

  • Building Slab pour​

  • On site utilities

  • Fire Dr Fill/Grading

  • Water main testing (3rd St & Cypress)

  • Pine sewer install

​

Week of 9/8

  • Complete Pine sewer​

  • Fire Dr Storm

  • Onsite Utilities

​

Week of 9/15

  • Pine Storm Install

  • 3rd/"Old Cypress" junction install

  • SNO PUD setting power poles

  • Onsite Utilities

  • Building slab secondary finishing (grinding)

AUGUST 6, 2025

~ Schedule Update 8.6.2025 ~

Week of 8/11

  • On site utility install 

  • Continue Cypress Sewer 

  • Resume Service/ Hydrant install @ 3rd St.

 

Week of 8/18

  • On site utility install 

  • Prepare and place building slab on grade (4")

  • Complete Cypress Sewer 

  • Start Water Main on Cypress â€‹

​

Week of 8/25

  • Prepare and place app bay slab on grade (8")

  • On site utility install 

  • Start Pine Ave Sewer â€‹

​

Week of 9/1

  • On site utility install

  • Slab on grade cure 

  • Continue Pine sewer 

JULY 30, 2025

~ Schedule Update 7.30.2025 ~

Week of 8/4

  • Prepare for concrete flat work

  • Start of onsite Utilities 

  • Start of Cypress Sewer 

​

Week of 8/11

  • Continue Cypress Sewer 

  • 3rd St. Hydrant/ service install 

  • Continue on site utilities 

  • Install Cap Break/ Vapor Barrier 

​

Week of 8/18

  • Fill & Test 3rd St. Water 

  • Finish Cypress Sewer 

  • Start Watermain on 3rd St. West of Pine/ Cypress 

  • Continue on site utilities 

  • Place 4" Slab on grade- concrete flat work

​

Week of 8/25

  • Continue Cypress water main install 

  • Conduct 3rd St Tie-ins 

  • Set Pine sewer bypass system up 

  • Continue on site utilities 

JULY 24, 2025

~ Schedule Update 7.24.2025 ~

Week of 7/28

  • Placement of the remaining foundation concrete 

  • Prepare Interior Building Subgrade 

  • Continue waterline on 3rd (crossing pine headed east bound on 3rd)

  • Start install of Old Cypress Sewer 

  • 4th St Water tie in 

  • 4th St Pavement Restoration 

 

Week of 8/4

  • Start onsite Storm 

  • Finish Old Cypress Sewer 

  • Move sewer bypass to Pine Ave 

  • Start Water Main on Old Cypress 

 

Week of 8/11

  • Prepare for Slab on grade 

  • Complete Water on Old Cypress 

  • Start Sewer on Pine 

  • 3rd St water tie in 

  • Pavement restoration on 3rd St 

 

Week of 8/18

  • Place Building Slab on Grade 

  • Start Framing Structure 

  • Start Water on Pine Ave 

  • Complete Sewer on Pine Ave 

JULY 10, 2025

~ Schedule Update 7.10.2025 ~

Week of 7/14

  • Start of foundations

  • Install of water services on 4th/prepare for testing

  • Start of "old cypress" sewer system
     

Week of 7/21

  • Station foundation work

  • Complete "old cypress" sewer system

  • Start 3rd St. water main​

​

Week of 7/28

  • Continue foundation work

  • Start Pine sewer

  • Install water services on 3rd St.
     

Week of 8/4

  • Continue foundation work

  • Complete Pine sewer

  • Complete 3rd St. water

JUNE 27, 2025

~ Schedule Update 6.27.2025 ~

Week of 6/30

  • No major activities
     

Week of 7/7

  • Dirt work on site

  • Infrastructure work
     

Week of 7/14

  • Footing excavation will begin 

  • Start footings  

  • Water main install on 4th to begin 

  • Sewer main on site between 3rd and 4th to begin 
     

Week of 7/21

  • Complete water main of 4th 

  • Continue Footings 

JUNE 11, 2025

~ Schedule Update 6.11.2025 ~

Week of  6/16

  • Wrap up preload placement/ ensure pile is neat 

  • Continue to monitor settlement

  • Haul off of top soil pile

 

Week of 6/23

  • Continue to monitor settlement

  • start water line on 4th Ave between Maple & Lincoln 

 

Week of  6/30

  • Continue to monitor settlement

  • Install, test, & Inspect water main on 4th Ave between Maple & Lincoln 

 

Week of 7/7

  • Continue to monitor settlement

  • Backfill water main on 4th Ave between Maple & Lincoln 

  • Begin water stubs on 4th Ave between Maple & Lincoln 

MAY 28, 2025

Basic Site prep and mobilization will begin on June 2nd. It will last around 2 weeks. The next phase will be the hauling (dump trucks) of fill into the site, which will also take about 2 weeks. Road and Utility work will likely begin in July after the Holiday. As we have more detailed information, we will update everyone.

~ Schedule ~

Friday 5/30/25

  • First couple pieces of equipment will be brought out to the site and stored

​

Week of 6/2/25

  • The earth working crew will be on site

  • Site fence will be installed

​

Week of 6/9/25

  • Begin to clear the site

  • Light trucking begins

  • Begin placement of structural fill

  • More trucks will start to show up

​

Week of 6/16/25

  • Heavy Truck presence remains

MARCH 29, 2025

***GROUND BREAKING CEREMONY***
 

For those who missed it, our ground breaking ceremony was a huge success! We were truly honoroed to see so many people taking time out of their day to join us in this momentous event.

 

While there are so many groups to thank for every effort put in to making this project come to life, we wish to make a special shout out to Jake Hensrude of ACE Equipment Rentals in Snohomish. Because of ACE's gracious donation, including delivery and pick up, the ground breaking was very unique with our very own GOLD excavator buckets! It was truly quite a hit!! Thank you so very much for your generosity and help in making Saturday truly memorable.

 

We also wish to extend our thanks to our Board of Commissioners, the City of Snohomish, the Snohomish Film Company, past and present elected officials, and so many more. The list truly does go on and on...

 

​

TIMELINE

New41.jpg

 

PINE AVENUE
DEVELOPMENT TIMELINE

​

​

04/09/2024       Live Fire Training Begins

02/13/2024       Daily Training Begins

01/20/2024       Property Vacated by Tenants

12/13/2023      Security Fencing in Place 

11/20/2023       Property Purchased

​

​

bottom of page