top of page

4th Street -
Civic Campus

LATEST
NEWS/UPDATES 

Entry Perspective (larger resolution) with sky.jpg

Here you will find any and all information on our current progress and operations regarding the 4th Street Property.  This site is best viewed in DESKTOP MODE.

Next Up...

If you wish to see how the Fire District and the City's individual projects will look upon completion, thus forming the Civic Campus, follow the link below.
https://www.snohomishwa.gov/817/Public-Safety-City-Services-Campus

4th Street
Fire Station Progress
7.21.2025 - 7.25.2025

JULY 24, 2025

~ Schedule Update 7.30.2025 ~

Week of 8/4

  • Prepare for concrete flat work

  • Start of onsite Utilities 

  • Start of Cypress Sewer 

​

Week of 8/11

  • Continue Cypress Sewer 

  • 3rd St. Hydrant/ service install 

  • Continue on site utilities 

  • Install Cap Break/ Vapor Barrier 

​

Week of 8/18

  • Fill & Test 3rd St. Water 

  • Finish Cypress Sewer 

  • Start Watermain on 3rd St. West of Pine/ Cypress 

  • Continue on site utilities 

  • Place 4" Slab on grade- concrete flat work

​

Week of 8/25

  • Continue Cypress water main install 

  • Conduct 3rd St Tie-ins 

  • Set Pine sewer bypass system up 

  • Continue on site utilities 

JULY 24, 2025

~ Schedule Update 7.24.2025 ~

Week of 7/28

  • Placement of the remaining foundation concrete 

  • Prepare Interior Building Subgrade 

  • Continue waterline on 3rd (crossing pine headed east bound on 3rd)

  • Start install of Old Cypress Sewer 

  • 4th St Water tie in 

  • 4th St Pavement Restoration 

 

Week of 8/4

  • Start onsite Storm 

  • Finish Old Cypress Sewer 

  • Move sewer bypass to Pine Ave 

  • Start Water Main on Old Cypress 

 

Week of 8/11

  • Prepare for Slab on grade 

  • Complete Water on Old Cypress 

  • Start Sewer on Pine 

  • 3rd St water tie in 

  • Pavement restoration on 3rd St 

 

Week of 8/18

  • Place Building Slab on Grade 

  • Start Framing Structure 

  • Start Water on Pine Ave 

  • Complete Sewer on Pine Ave 

JULY 10, 2025

~ Schedule Update 7.10.2025 ~

Week of 7/14

  • Start of foundations

  • Install of water services on 4th/prepare for testing

  • Start of "old cypress" sewer system
     

Week of 7/21

  • Station foundation work

  • Complete "old cypress" sewer system

  • Start 3rd St. water main​

​

Week of 7/28

  • Continue foundation work

  • Start Pine sewer

  • Install water services on 3rd St.
     

Week of 8/4

  • Continue foundation work

  • Complete Pine sewer

  • Complete 3rd St. water

JUNE 27, 2025

~ Schedule Update 6.27.2025 ~

Week of 6/30

  • No major activities
     

Week of 7/7

  • Dirt work on site

  • Infrastructure work
     

Week of 7/14

  • Footing excavation will begin 

  • Start footings  

  • Water main install on 4th to begin 

  • Sewer main on site between 3rd and 4th to begin 
     

Week of 7/21

  • Complete water main of 4th 

  • Continue Footings 

JUNE 11, 2025

~ Schedule Update 6.11.2025 ~

Week of  6/16

  • Wrap up preload placement/ ensure pile is neat 

  • Continue to monitor settlement

  • Haul off of top soil pile

 

Week of 6/23

  • Continue to monitor settlement

  • start water line on 4th Ave between Maple & Lincoln 

 

Week of  6/30

  • Continue to monitor settlement

  • Install, test, & Inspect water main on 4th Ave between Maple & Lincoln 

 

Week of 7/7

  • Continue to monitor settlement

  • Backfill water main on 4th Ave between Maple & Lincoln 

  • Begin water stubs on 4th Ave between Maple & Lincoln 

MAY 28, 2025

Basic Site prep and mobilization will begin on June 2nd. It will last around 2 weeks. The next phase will be the hauling (dump trucks) of fill into the site, which will also take about 2 weeks. Road and Utility work will likely begin in July after the Holiday. As we have more detailed information, we will update everyone.

~ Schedule ~

Friday 5/30/25

  • First couple pieces of equipment will be brought out to the site and stored

​

Week of 6/2/25

  • The earth working crew will be on site

  • Site fence will be installed

​

Week of 6/9/25

  • Begin to clear the site

  • Light trucking begins

  • Begin placement of structural fill

  • More trucks will start to show up

​

Week of 6/16/25

  • Heavy Truck presence remains

MARCH 29, 2025

***GROUND BREAKING CEREMONY***
 

For those who missed it, our ground breaking ceremony was a huge success! We were truly honoroed to see so many people taking time out of their day to join us in this momentous event.

 

While there are so many groups to thank for every effort put in to making this project come to life, we wish to make a special shout out to Jake Hensrude of ACE Equipment Rentals in Snohomish. Because of ACE's gracious donation, including delivery and pick up, the ground breaking was very unique with our very own GOLD excavator buckets! It was truly quite a hit!! Thank you so very much for your generosity and help in making Saturday truly memorable.

 

We also wish to extend our thanks to our Board of Commissioners, the City of Snohomish, the Snohomish Film Company, past and present elected officials, and so many more. The list truly does go on and on...

 

​

JULY 24, 2024

Plans are being finalized! The District is currently and frequently meeting with the architect to confirm final details and we are planning to break ground and start construction in the first quarter of 2025!

TIMELINE

New41.jpg

 

PINE AVENUE
DEVELOPMENT TIMELINE

​

​

04/09/2024       Live Fire Training Begins

02/13/2024       Daily Training Begins

01/20/2024       Property Vacated by Tenants

12/13/2023      Security Fencing in Place 

11/20/2023       Property Purchased

​

​

bottom of page